You can see the building coming up as you pay. Once the structure is complete, you feel that the construction is at snail's speed. You can see that the money is flowing out but you feel nothing is happening,
But yes there are many things that happening at that stage, the plastering work which can take more than a month, then the plumbing, electrical wiring, after that flooring.......
One thing that I realised during the construction is that, its always better for you to be present during the key days, like the days of concreting.
While the concreting is happening you need to take care of a few things.
1) if the casting is going on for an exposed slab, make sure that water proof solution is mixed. They normally mix it in the water that they use during mixing
2) Make sure that the sand is clean, any foreign decay-able things like wood piece cloth piece etc can cause leak if they get in to the mixture, they normally get in to the mixture from the sand.
3) Make sure that the labors are using vibrators properly to get the concrete in to all corners. the vibrator should touch the steel rods so that the concrete gets below them
4) Make sure that proper curing is done.
Its an un-written rule that you should provide food for the labors on that day. The supervisor normally collect some money towards that (around 2500/-) Or if you are comfortable you can very well arrange for the food. You never know what %ge of the money goes to the actual food expenses.
So my house is now slowly getting it's shape.
Week 2 |
You can see that the sump is the fist thing to be built (or rather dug) it is because you need water, a lot of water during construction so you got to keep the sump filled always.
Week 4 |
Week 6 - ready for first slab casting |
Ready for Second slab casting |
Final slab casting done |
Elevation work in progress |
Elevation work getting completed |
Even though its the responsibility of the contractor to make sure that the labors are safe. Its always better you too check the scaffolding's are strong and proper. The last thing you want to happen during your construction is to see some one getting hurt during that. And there is a payment that you need to make to the labor board during the plan approval process. That goes towards to the welfare of the labors.
Plastering done and ready for the painting |
Never rush during plastering, let the labors take their own time and pace. And yes make sure proper curing is done here as well.
After plastering they give rough finish for the exterior walls and walls on which any types of cladding or tiles are to be applied.
The interior walls are finished with lime (a calcium mixture). it is better to get this finishing work is done in the night, when the work is done with a strong artificial light source kept in a corner, it will give a better understanding of the finish and smoothness of the wall. With the putty applied on the wall this will give satin smoothness even with normal wall paints.
The final product |
This is the really good informative Post on Blogger and I really like to read it. Thanks for Presenting with us.
ReplyDeleteWater Well Drillers in Bangalore
Mahidhara's villas are available in peaceful location of Bangalore…
ReplyDeleteVilla in Electronic City Bangalore
Quality Solutions Scaffolding
ReplyDelete6 Masefield close
DA82DG
020 8311 3169
Thanks for sharing this useful information
ReplyDeleteBudget Flats for sale in Bangalore
M sand is superior quality, engineered crushed stone sand which is highly suitable for construction. M sand comes in two types for concrete and plastering.
ReplyDeleteIt has benefits over river sand and is slowly gaining its importance. Get more details:Sand Manufactures in bangalore